Customer |
Name Works |
Scope Of Work |
Location |
Working Period |
Value (THB.) |
PTT Maintenance & Engineering Co., Ltd. |
Install Fall Protection at RCL Project |
Civil, Steel Structure and E & I Work |
PTTGC (RCL) |
March 2018 ~ May 2018 |
4,200,000.00 |
PTT Maintenance & Engineering Co., Ltd. |
Mechanical Seal Plan 52 Reliability Improvement ARO Project |
Mechanical Erection and Installation |
PTTGC Branch 4 ( Aromatic ) |
2018 ~ June 2019 |
6,800,000.00 |
PTT Maintenance & Engineering Co., Ltd. |
Relocate Underground Facilities for New Rack Room (I-1) and Demolish Pump Section Line for ORP Project |
Piping and Civil Construction Work |
PTTGC2 (I-1 Plant) |
Januery 2018 ~ Januery 2019 |
2,480,522.00 |
Sinopec Engineering Group (Thailand) Co., Ltd. |
Mechanical Erection and Installation Work for RDCC Catalyst Cooler Project |
Mechanical Erection and Installation |
IRPC’s Refinery Plant, Rayong |
June 2018 ~ Januery 2019 |
88,823,279.59 |
PTT Maintenance & Engineering Co., Ltd. |
Demolish and Reroute Domestic Sewerage Pipeline for ORP Project |
Piping Construction Work |
PTTGC2 (I-1 Plant) |
March 2018 ~ June 2019 |
3,750,000.00 |
Rayong Terminal Co., Ltd. |
BCM-Pipe Rack Extension Construction 2 RTC-Piperack Extension Construction Area : RTC-BX-01 to BX-05 |
Piping and Steel Structure Construction Co., Ltd. |
RTC Plant |
Januery 2018 ~ June 2018 |
10,500,000.00 |