Customer |
Name Works |
Scope Of Work |
Location |
Working Period |
Value (THB.) |
PTT Maintenance & Engineering Co., Ltd. |
Install Roof and Odor Unit for G- 1134-V-1 and G1144-V1 Project |
Mechanical, Steel Structure and Piping Construction Work |
PTTGC (I-4 Plant) |
Januery 2019 ~ 2019 |
9,950,000.00 |
PTT Maintenance & Engineering Co., Ltd. |
Hight Pressure Steam Project (Package 1) |
Piping and Steel Structure Construction |
PTGC Branch 2 (I-1 Plant) |
May 2019 ~ November 2019 |
36,580,000.00 |
PTT Maintenance & Engineering Co., Ltd. |
HDD for Ethylene and Propylene UG Pipeline |
HDD Piping and Civil Construction Work |
PTTGC6 |
March 2019 ~ July 2019 |
39,600,000.00 |
PTT Maintenance & Engineering Co., Ltd. |
Replace Equipment Around C2 Splitter of I-4/1 Project |
Piping, Mechanical and Steel Structure Work |
PTTGC3 (I-4 Plant) |
2019 ~ Febluery 2020 |
9,850,000.00 |
PTT Maintenance & Engineering Co., Ltd. |
Replace Equipment Around Cold Flare Project |
Mechanical, Steel Structure and Piping Construction Work |
PTTGC3 (I-4 Plant) |
2019 ~ Febluery 2020 |
8,797,035.00 |
PTT Global Chemical Public Company Limited |
GC4-TA2019-S08A Piping Hot & Piping Cold Work A |
Piping and Mechanical Service Work |
PTTGC (I-4 Plant) |
Januery 2019 ~ June 2019 |
11,100,000.00 |
PTT Maintenance & Engineering Co., Ltd. |
Install Heating Facility in FO Tank Project |
Civil and Steel Structure Construction Work |
PTTGC6 Refinery Plant, Rayong |
June 2019 ~ November 2019 |
36,580,000.00 |
PTT Global Chemical Public Company Limited |
Civil, Mechanical and Piping fabrication and installation O-P3 of the 4th charge gas dryer project |
Civil, Mechanical and Piping Construction Work |
PTTGC6 (Refinery Plant) |
October 2019 ~ December 2019 |
48,000,000.00 |
PTT Maintenance & Engineering Co., Ltd. |
Mechanical, Piping, Civil and Structure, Instrument Work for Treated Water Supply from GUSCOTie-in for ORP project |
Civil, Structure, Mechanical and Piping Construction Work |
PTTGC2 (I-1 Plant) |
October 2019 ~ Januery 2020 |
43,200,000.00 |
PTT Global Chemical Public Company Limited |
Service OLE2-P03B-Piping Repair Backlog for Turnaround Year 2020 at GC3 |
Piping Construction Work |
PTTGC3 (Olefins I-4 Plant) |
Febluery 2019 ~ July 2020 |
10,500,000.00 |
PTT Maintenance & Engineering Co., Ltd. |
Civil Work Package (CB) |
Civil and Steel Structure Construction Work |
PTTGC6 Refinery Plant, Rayong |
May 2019 ~ April 2020 |
58,900,000.00 |