Customer Name Works Scope Of Work Location Working Period Value (THB.)
Thai Taffeta Company Limited Piping Work of Poly Plant Project Piping Fabrication and Installation Work Thai Taffeta Company Limited October 2013 ~ December 2013 17,700,000.00
PTT Maintenance and Engineering Company Limited Chain Link Fence-ACE-BVOSBL Project Civil, Steel Structure and Construction Work PTT Maintenance and Engineering Company Limited May 2013 ~ July 2013 1,750,000.00
Bangkok Polyethylene Public Company Limited Engineering Package 2 For T/A BPE 2 Piping Installation Work BPE-2 Plant May 2013 ~ July 2013 2,529,200.00
Right Solution Public Company Limited Construction Work Pipe Receiver & Pig Launcher Material Supply and Construction Work PTTGC I-4 Plant Febluery 2014 ~ March 2014 1,255,147.00
Thai Plastic and Chemicals Public Company Limited Improving Waste Water System Piping Installation Work  Thai Plastic and Chemicals Public Company Limited Febluery 2010 ~ April 2010 4,919,063.00
Thai Plastic and Chemicals Public Company Limited Piping and Installation Work for Improving Waste Water System VCM 1 Piping Installation Work Thai Plastic and Chemicals Public Company Limited Febluery 2010 ~ April 2010 2,997,489.00
Glow Energy Public Company Limited Main Steam and Return Condensate Pipelines for Dow Chemicals Piping Steel Structure Construction Work Glow Energy Public Company Limited November 2009 ~ October 2010 185,272,513.00
PTT Global Chemical Public Company Limited Shutdown EPC ER OL4-058-10, 044-11, 120-07 T/A 2013 PTTGC Mechanical and Construction Work PTT Global Chemical Public Company Limited April 2013 ~ 2013 1,630,000.00
PTT Polyethylene Company Limited Hiring Construction ET-001-12 PTTPE Piping/Steel Structure/ Construction and Civil Work PTT Polyethylene Company Limited April 2012 ~ July 2012 5,086,841.00
Glow Energy Public Company Limited MP Steam Back Up Pipeline to Deaerator of Cogeneration Tank Unit 1&2 Piping Structure/Construction Work Glow Energy GSPP2 Plant April 2012 ~ 2012 5,900,000.00
Gheco-One Company Limited The Wind Shield at East Side of Gheco-One‘s Coal Pile Project Steel Structure, Construction and Civil Work Glow Energy GSPP3 Plant April 2012 ~ 2012 41,330,000.0
PTT Global Chemical Public Company Limited Hiring EPC MOD. U-001-13 เปลี่ยนชนิด Filter Distributor Maintenance and Mechanical Work PTT Global Chemical Public Company Limited March 2013 ~ 2013 2,774,000.00
Thai Polyacetal Co., Ltd Installation for Formalin’s Loading Facility and Equipment to Truck Installation Equipment TPAC May 2017 ~ June 2017 3,780,000.00
Bangkok Industrial Gas Company Limited Steel Structure for Pipe Bridge and Pipe Racks PTTUT Piping Modify, Fabrication and Installation, Steel Structure and Foundation Bangkok Industrial Gas Company Limited Febluery 2012 ~ June 2013 2,480,000.00
Glow Energy Public Company Limited The New Coal Roof Expansion for GSPP3's Coal Pile Steel Structure Installation and Construction Work Glow SPP3 Plant December 2013 ~ July 2014 49,900,000.00